Kigali Network Strenghening 2

Project Category Transmission , Medium Voltage
Project Name Kigali Network Strenghening 2
Donor/Funder World Bank
Effectiveness Date 01 Mar 2018
Closure Date 31 Jan 2019
Status Ongoing

Scope

Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus.
This Project is divided in  3 lots:

  • 1st lot: Supply of underground cables  
  • 2nd lot:  Design supply and installation for the overhead line.
  • 3rd lot: installation of under ground cables

Geographic Coverage

Kigali City

Photos